Lake dredging referendum price tag could be $1.75 million

by GINA DUWE ( Contact )   Wednesday, Aug. 27, 2008
ADVERTISEMENT
 
Evansville's Lake Leota is now a large field of brush and weeds after it was drained in 2005. The city is considering a referendum to approve money for dredging the lakebed and restoring Lake Leota.

Evansville's Lake Leota is now a large field of brush and weeds after it was drained in 2005. The city is considering a referendum to approve money for dredging the lakebed and restoring Lake Leota.

Evansville's Lake Leota has been a large field of brush and weeds since it was drained in 2005.

Evansville's Lake Leota has been a large field of brush and weeds since it was drained in 2005.

— Evansville residents might vote Nov. 4 whether Lake Leota should be dredged at a cost of no more than $1.75 million.

The public works committee recommended the following wording for a November advisory referendum: “Shall the Evansville Common Council approve spending an amount not to exceed $1.75 million in order to restore Lake Leota?”

The city council will vote on the referendum at its meeting Tuesday, Sept. 9.

The cost of the project still is subject to change and is based on city negotiations to dump sediment dredged from the lake onto adjoining land. Officials will work with engineers at Vierbicher Associates in the coming days to nail down the cost.

Mason Braunschweig and Janis Ringhand, who are members of the public works committee and the council, both said Tuesday night they didn’t want the cost to be so high that it would scare people, but they didn’t want it too low that it wouldn’t cover the cost of the project.

“It has to be as accurate as possible,” Braunschweig said.

Gilbert Wiedenhoeft, a member of the Save Our Lake Environment group, questioned whether the dollar amount had to be exact because the referendum isn’t binding.

“It’s not binding, but boy it’s pretty telling,” Braunschweig responded.

“It’s our credibility for how we proposed the issue and carried through, kept our word,” Ringhand added.

Public debate has centered on a mix of numbers.

In February, Vierbicher presented a plan to dredge the lake for $1.7 million to $2.6 million, with the range depending on how far 200,000 cubic yards of lakebed material would have to be transported.

The price tag now is on the lower end because City Administrator Dan Wietecha reported Tuesday he is nearing agreement with nearby landowners to place the sediment on their property.

In July, the park board recommended the council move forward with dredging without a referendum at a cost of $1.7 million, depending upon the city’s ability to dump dirt on neighboring property owners’ land.

If the $1.75 million price tag for the referendum changes, it will be discussed at the city council meeting Sept. 9. Referendum wording for the ballot needs to be delivered to the Rock County Clerk’s Office by Tuesday, Sept. 23.

“The council’s pretty much our last chance to get (the dollar amount) right,” Braunschweig said.

Committee members discussed directing the city to place the project out for bids at its September meeting. If the proposed referendum is approved Nov. 4, the council could award a bid at its Nov. 11 meeting.

reader COMMENTS

Before you post a comment, consider this:

Note: WCLO.com does not condone or review every comment. Read more in our User Policy Agreement
  • Keep it clean. Comments that are obscene, vulgar or sexually oriented will be removed. Creative spelling of such terms or implied use of such language is banned, also.
  • Don't threaten to hurt or kill anyone.
  • Be nice. No racism, sexism or any other sort of -ism that degrades another person.
  • Harassing comments. If you are the subject of a harassing comment or personal attack by another user, do not respond in-kind.  Hit the "Suggest Removal" button on offensive comments.
  • Share what you know. Give us your eyewitness accounts, background, observations and history.
  • Do not libel anyone. Libel is writing something false about someone that damages that person's reputation.
  • Ask questions. What more do you want to know about the story?
  • Stay focused. Keep on the story's topic.
  • Help us get it right. If you spot a factual error or misspelling, email programming@wclo.com or call 608-752-7895.
  • Remember, this is our site. We set the rules, and we reserve the right to remove any comments that we deem inappropriate.

Post Comment

Commenting requires registration.

Username:
Password: (Forgotten your password?)

Comment:

ADVERTISEMENT