Alliant makes progress on Paddock Solar Project

Another Rock County Solar Project located outside of Beloit is making progress towards completion at the end of this year.
Alliant Energy Representative Chris Caporale says 60% of the site work has been completed and about 30% of the underground electrical cable has been installed.
Caporale  says the project is expected to be operational by December of this year, but they could potentially begin putting out electricity in a test setting in July or August.
According to Alliant, once completed the project will generate enough energy to power around 17,000 homes.